We are proud to be able to share these photos of the progression of the Aldi Abergavenny project which was handed over this afternoon. The project comprised Aldi building a new ATS, demolishing the old tired ATS building which then allowed an extension to the existing Aldi store, car park and associated external works.
The pictures show the progression from the initial architects' concept to the finished store extension today 12.12.22.
The Project Team comprised; Arc Bauen Construction Managers, BMT Mechanical and Electrical Consultants, Craddys Structural Engineers, Kendall Kingscott Architects, Owen Associates Quantity Surveyors, K2 Refrigeration Consultants.
The project (including the ATS) started the end of Jan 2022 and has taken just under 11 months to complete.